(Contents)

Time-Management Reports

The Time-Management report system provides access to a suite of reports that can be run for each company, with drill-down capabilities to resource and analysis code level. These can be printed or exported to an Excel spreadsheet.

Tip: Each report has hover-text help which is displayed if you hover over a hover-text RedArrow.gif button. This is intended to help you to understand what the calculations are for each heading in the report. Hover-text help cannot be printed.

To run a Time-Management report:

  1. From the Rev.8 Master Menu, select the Workshop loading option and Company you require.
  2. The WORKSHOP LOADING menu is displayed.

  3. Select Reports & enquiries.

    The WL REPORTS AND ENQUIRIES menu is displayed.

  4. Select the Time-Management report option.

    The Time-Management Report form is displayed.

Time-Management Report Form

This form is displayed when you click Workshop loading > Reports & enquiries > Time-Management report. It enables you to display the time-management reports and run, print or export them.

Menu Bar and Toolbar:

Menu bar Toolbar Action
File > Exit Exit.gif Returns you to the Workshop Loading REPORTS AND ENQUIRIES menu.
File > Refresh Refreshes the current selected report.
File > Print Print.gif Prints the current selected report page to the selected printer, which must be capable of receiving Print Manager formatted data.
File > Kprint Preview PrintPreview.gif Preview the current selected report page using Print Manager.
File > Export to Excel > Full/Formatted/Unformatted Export.gif Exports the currently selected report page to an Excel spreadsheet.

Note: This function is not enabled when the number of columns defined in the report is greater than 256, which is the maximum number of columns that Excel can handle.

File > Graph > Utilisation/Productivity/Efficiency Graph.gif Shows the displayed data in graphical form.

Note: Not all reports can be graphed. When the Graph button is clicked, three option buttons enable you to choose between Bar, 3D Bar and Line graphing.

File > Change printer Printer.gif Displays the Printer selection list, enabling you to change the currently selected printer.
File > User permissions   Displays the Set the user permissions on reports form, enabling you to change the user permissions.
File > Help Help2.gif Displays this help topic in a web browser.

Selection Group:

Buttons:

Pin/Un-pin selection frame: When the selection frame is pinned the auto-hide of the Selection frame is disabled. When the selection frame is un-pinned the auto-hide of the Selection frame is enabled, after an idle period the Selection frame is minimised automatically. Click the Click the Pinned PinnedSelectionFrame.gif or Unpinned Un-pinnedSelectionFrame_000.gif button to change from one state to the other.

Manually minimize/Manually maximize: When the Manually minimize LeftBlueArrow.gif button is clicked the Selection frame is hidden. When the Manually maximize TestExecute_000.gif button is clicked it is displayed. Click the button to change from one state to the other.

Tabs:

The Selection group contains two tabs:

Properties Tab

You can use this tab to control the formatting of your reports. Make changes by clicking the Setting of the property you want to change and clicking the drop-down DropDown.gif or ellipsis Ellipsis.gif button to make your selection.

Any changes to the settings are stored in the users profile when you leave the program and loaded when you enter.

Tip: For each property setting, help text is displayed at the bottom of the Selection frame.

Generic profile:

Property

Description

Settings

Auto hide selections frame

Should the selection frame be minimized automatically after 15 idle seconds?

On
Off

Colour schema for the dashboard

Sets the dashboard colour scheme

Yellow to Aqua
Red to Blue
Red to Green

Report date settings

What should be done with the report start and end dates when starting the program?

Last used dates
Current month to yesterday
Current month to today

Report company style

When starting the program, should the company be shown in a tree structure or in a grid?

Company in tree
Company in report

Generic properties:

Property

Description

Settings

Start date

Start date for the report

Manually entered date
Date selected with calendar [...] button

End date

End date for the report

Manually entered date
Date selected with calendar [...] button

Time-Management properties:

Property

Description

Settings

Time presented in

How should times be displayed?

Decimal time
Clock time

Show sales ledger categories

Should only the sales ledger categories analysed in the generation run be displayed, or all that are set up in the system whether they are used or not?

All available
Only the used

Show idle codes

Should only the idle codes analysed in the generation run be displayed, or all that are set up in the system whether they are used or not?

All available
Only the used

Show department codes

Should only the SO departments analysed in the generation run be displayed, or all that are set up in the system whether they are used or not?

All available
Only the used

Show franchise letters

Should only the franchise letters analysed in the generation run be displayed, or all that are set up in the system whether they are used or not?

All available
Only the used

Show clock details

Should clock details on date level be displayed according to clock time or type of work?

On time-in
On work-type

Calculate in progress labour with

Should the times used in the calculations of non-invoiced labour lines be based on the time allowed from the labour record, or the real time taken from the clocking?

Allowed from labour
Taken from clocking

Include in progress labour

Which labour lines should be included in the report?

Both invoiced and In progress labour lines
Only Invoiced labour lines
Only Outstanding labour lines

Unproductive idle in overtime

Should the unproductive idle codes be included in or excluded from the overtime calculations?

Include unpro idle clocking's in overtime
Exclude unpro idle clocking's from overtime

Display mechanics

Should all mechanics, only the non-productive ones or only the productive ones be included in the report?

All mechanics
Only productive mechanics
Only non-productive mechanics

Time offset error reporting

When time is missed during the shift an offset can be set, with nothing below this value being reported.

0.00 Minutes
Manually entered number of minutes

Sold time calculation

Should normal time allowed or bonus time be shown on the report?

Allowed time
Bonus time

Reports Tab [left-hand pane]

The available reports are listed on the Reports tab and can be selected from the report tree, by clicking expand Expand2_000.gif to expand a line and collapse Collapse.gif to collapse it. The reports available may include the following:

System.gifSystem:

The report displays the company system setup starting with the current module.

CompanyGroup.gif Module setup overview:

All the company modules required for the reports are displayed in the Report tab in the right-hand side pane. For the companies involved it provides period date information if applicable and what data is used.

Modules:

Module: Displays the module mnemonic.

Description: Displays the description of the module.

Include companies:

Company: Displays the company number.

Description: Displays the description of the company.

 

Clocking.gif Time Management:

Clicking expand Expand2_000.gif expands the analysis report by Company.

Clicking collapse Collapse.gif collapses the analysis report back to an overall summary.

See Report column headings for details of the report.

 

Clocking.gif Company / Dealer:

Clicking expand Expand2_000.gif expands the analysis report by Company.

Clicking collapse Collapse.gif collapses the analysis report back to an overall summary.

See Report column headings for details of the report.

 

  Details of all clocking's:

This report displays all the details from the resource calendar, clocking's and the type of work, with details on sales ledger account category, idle codes and adjusted availability.

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Total of all clocking's by:

This report will show all the totals on calendar, clocking's, type of work.

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Totals on Departments by:

Time that has been clocked on WIPs, split up in the various Point-of-Sale department codes. The time taken and allowed from the clock record is shown and used for the efficiency calculation.

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Totals on Franchises by

Time that has been clocked to WIPs, split up in the various franchise letters. The time taken and allowed from the clock record is shown and used for the efficiency calculation. 

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Payroll statistics by:

For the overtime payment the report calculates the time taken above the specified shift.

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Performance by:

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Clocking's by Sales Type by:

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Attendance by:

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Performance Ratios by:

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Idle Time Analysis by

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Absence Analysis by:

This report displays any adjusted availability made to each resource whether absence or overtime.

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report.

 

Dashboard:

The report dash board displays four different calculations: Utilisation, Productivity, Efficiency and Performance for each resource in each company

Click expand Expand2_000.gif to analysis the report by Analysis code or Resource.

Click collapse Collapse.gif to return to the summary report.

See Report column headings for details of the report

Tip: Hover over the RedArrow.gif icon to display the calculations used for each option.

Information.gif Generation problems:

When there are problems found in the generation process these are reported as either warnings or fatal errors. This report explains the problems found with an explanation of the problem and, when possible, you can display the details by clicking the link.

Warnings:

Shift duration: There is a difference between the time returned from the standard workshop loading function and the time count on the shift including the adjusted availability.

One of the reasons this can happen is adjusted availability that is marked as = (equals). The report program uses the original shift pattern for calculation which the core routine ignores.

Fatal problems:

Missing time during shift: When during a shift there are periods that are not represented by a clocking, the system marks it as a fatal problem, specially for overtime calculations.

Report pane: At the bottom of the report a line of information is shown detailing the report start date, report end date and the current selected printer.

Tolerances Tab

You can use this tab to control the formatting of your reports. Make changes by clicking the Setting of the property you want to change and clicking the drop-down DropDown.gif or ellipsis Ellipsis.gif button to make your selection.

Any changes to the settings are stored in the users profile when you leave the program and loaded when you enter.

Tip: For each property setting, help text is displayed at the bottom of the Selection frame.

Property

Description

Settings

Use tolerances ?

Are tolerances in use?

On, Off

Before start of shift

Number of minutes considered as an acceptable tolerance before the start of a shift

Required minutes

After start of shift

Number of minutes considered as an acceptable tolerance after the start of a shift

Required minutes

Before end of shift

Number of minutes considered as an acceptable tolerance before the end of a shift

Required minutes

After end of shift

Number of minutes considered as an acceptable tolerance after the end of a shift

Required minutes

Fixed lunch break?

Is there a fixed lunch, If Yes the following 4 items apply.

Yes, No

Before start of lunch

Number of minutes considered as an acceptable tolerance when a resource is clocked off for lunch

Required minutes

After start of lunch

Number of minutes considered as an acceptable tolerance when a resource is clocked off for lunch

Required minutes

Before end of lunch

Number of minutes considered as an acceptable tolerance before when a resource is clocked off for lunch

Required minutes

After end of lunch

Number of minutes considered as an acceptable tolerance after when a resource is clocked off for lunch

Required minutes

Tolerance for lunch

Number of minutes considered as an acceptable tolerance for lunch

Required minutes

Note: Hours and minutes are entered in the format HOURS.MINUTES.

Report Tab [right-hand pane]

Selecting a report from the tree in the Reports tab in the left-hand pane has the effect of displaying the specified information in the data grid on the Report tab in the right-hand pane. If this is the first time the report has been selected, the report generation form is displayed.

Tip: For some reports, the Shift details ShiftDetails.gif icon is displayed. Selecting it displays the shift and clocking details of that resource for that particular day in a new report tab called Detail - 1.

Displayed Reports (Freezing)

In the displayed report a special function can be used to freeze the displayed information on horizontal and vertical positions. This function is available if the unlock Unlock.gif icon is displayed in the top left-hand corner of the data grid.

By clicking blocks in the grey line, you can execute the freeze function. The block that is selected is marked with a key KeyThisVehicle.gif icon. Select the unlock Unlock.gif icon again and the report is displayed in the full grid.

Displayed Reports (Column Headings)

Drill:

You can expand and collapse the information in the data grid by clicking the buttons as follows:

You can click the hyperlinks (indicated with red underlining) for further information where available.

Note: There is no equivalent of the Back button used on internet browsers.

Item-description: Displays a list of resources for that particular company.

Badge:

Available: Displays the availability percentage of the resource.

Productive: Whether the resource is productive or not is indicated with a green Tick.gif.

Calendar settings:

Shift hours: Available hours on the shift, taking into account the extra availability.

Break hours: Un-available hours (breaks) defined in between the shift start and end.

Total hours: Total hours present, total of shift hours and break hours.

Shift days: Day counter for each day a valid shift is defined.

Point-of-Sale:

Clocked hours: Hours represented by the contents of the taken field on clock records.

Clocked days: Day counter for each day a valid clock record is found.

No. of WIPS: Counter for each WIP that is used for the first time in the clocking's file.

Tolerances:

Adjusted hours: Total POS clocked hours adjusted by the tolerance (Displayed as minutes)

Total variances: Total sum of the accumulated daily tolerance (Displayed as a decimal).

Variance Calendar and Point of Sale:

Calculation with the days and time setup in workshop loading and the actual clocking's made.

Variance in hours:

Lost: Hours lost with regard to the shift, which are the shift hours minus the clocked hours.

Extra: Extra hours with regard to the shift, which are the clocked hours minus the shift hours.

Variance in days:

Lost: Days lost with regard to the shift, which are the shift days minus the clocked days.

Extra: Extra days with regard to the shift, which are the clocked days minus the shift days.

Direct productive time:

Allowed: Time allowed from the clock record for the sales category

Taken: Time that has been clocked on WIPs for the sales categories.

Efficiency: Efficiency calculated with the Taken and Allowed time. The formula used is: Efficiency = round(( Allowed / Taken) *100, 2)

CaCash Sales:

Allowed: Time allowed from the clock record for the sales category.

Taken: Time that has been clocked on WIPs for the sales categories.

Efficiency: Efficiency calculated with the Taken and Allowed time. The formula used is: Efficiency = round(( Allowed / Taken) *100, 2)

Indirect productive time:

Productive idle time: Clocking's made on idle codes that are set up as productive. The time taken from the clock record is shown.

Non productive idle time: Time taken from the clock record for idle codes that are marked as non-productive on the idle time code record.

Adjusted availability: Adjusted availability used to change the defined shift for a resource and date, set to the reason code of the adjustment.

Totals: The totals for each Company are displayed at the bottom of the report.

Non-productive time:

Driving: Time taken from the clock record for idle codes that are marked as non-productive on the idle time code record.

Idle 1: Time taken from the clock record for idle codes that are marked as non-productive on the idle time code record.

Department times:

Taken: Time taken to action Workshop tasks for the selected department.

Allowed: Time allowed to action Workshop tasks for the selected department.

Efficiency: Efficiency to action clocked tasks for the selected department.

No of WIPs: Number of WIP clocked for the selected department.

Calculation:

Overtime: Time spent above the setup shift times (This may vary dependant upon Country).

Attendance

Shift: Available hours in shift, excluding the extra availability.

Attended: Hours represented by the contents of the taken field on the clock records.

Idle: Non-productive hours represented by the contents of the taken field on the clock records.

Clocking's:

Allowed: Time allowed from the contents of the allowed field on the clock records.

Taken: Time taken from the contents of the taken field on the clock records.

Financials:

Cost: Time taken multiplied by the mechanic hour cost as set on the mechanic record.

Revenue: Time allowed multiplied by the rate for the WIP line.

Profit: Result of the labour revenue minus the labour cost.

Recovery rate: Labour revenue divided by the time allowed.

Total direct productive time:

Taken: Total time taken to action Workshop tasks for the selected department.

Allowed: Total time allowed to action Workshop tasks for the selected department.

Efficiency: Total efficiency to action clocked tasks for the selected department.

Recovery rate:

Performance:

Utilisation %: Percentage of the calendar hours less idle hours divided by the calendar hours.

Productivity %: Productive hours divided by the calendar hours less idle hours.

Efficiency %: Percentage of sold hours against the productive hours.

Planned hours:

Shift days: Day counter for each day a valid shift is defined.

Shift hours: Available hours on the shift, taking into account the extra availability.

Break hours: Un-available hours (breaks) defined in between the shift start and end.

Total hours: Total hours present, total of shift hours and break hours.

Actual Hours:

Taken: The actual time taken from the clock record.

Productive idle : Clocking's made on idle codes that are set up as productive.

Non productive: Time taken from the clock record for idle codes that are marked as non-productive on the idle time code record.

Adjusted: Adjusted availability used to change the defined shift for a resource and date, set to the reason code of the adjustment.

Lost: Hours lost in respect to the shift, which are the shift hours minus the clocked hours.

Extra: Hours extra in respect to the shift, which are the clocked hours minus the shift hours.

Utilisation %:

Utilisation:

Var to Avg:

Var to Low:

Var to High:

Productivity %:

Productivity:

Var to Avg:

Var to Low:

Var to High:

Effeciency %:

Efficiency:

Var to Avg:

Var to Low:

Var to High:

Related Topics:

User permissions

(Contents)